Hibbing Water Main Capital Improvement Plan
Project Status: Active – ~66% Complete

Existing Infrastructure: 1920’s installed 6″ cast iron water main
Qualifying Factors: This project was selected due to the age of existing infrastructure, importance to system operations, and alignment with City of Hibbing Paving Plan.
Scope of Work: Direct replacement of ~1,500 Linear Feet of water main and ~1,000 Linear Feet of steam line.
Cost: Preliminary Engineering Estimate of $1.7 million
Weekly Project Updates
- Week of August 10th (Planned)
- Pouring concrete curb and gutter
Past weeks –
- Week of August 3th
- Pour steam vault lid on vault N7.
- Pour steam duct top on exposed duct located to the north of Lincoln Elementary.
- Continue roadway preparation work
- Week of July 27th
- Walls on steam vault N8 have been poured.
- Lids on steam vaults N6, N8 and N9 have been poured.
- Steam vaults N4A and N6 have been backfilled.
- City of Hibbing storm sewer on the east side of Brooklyn has been completed.
- Week of July 20th
- Pour steam vault walls on N8/N9.
- Pour steam vault lids on N7-N9.
- Continue roadway preparation work.
- Continue internal steam work as vaults and tunnel are exposed.
- Week of July 13th
- Saw cut and removed lids of steam vaults in Brooklyn Drive (N8 & N9).
- Continued roadway preparation work.
- Connected new 2” water service to 2239 E Beltline Garage.
- Removed temporary water system.
- Continued steam tunnel and vault internal work.
- Week of July 6th
- Bacteria testing on new 12” watermain on E 23rd Street.
- Continued storm work near Brooklyn Drive.
- Exposed steam vaults and tunnel in Brooklyn Drive (N8 and N9).
- Continued steam work on exposed tunnels and vaults.
- Roadway sub cut work starting west working east on E 23rd St.
- Formed and poured steam vault walls on Vaults N5 and N6.
- Week of June 29th
- Continued storm work in Brooklyn Drive.
- Connected new hydrant east of 2239 E Beltline Garage along TH 169.
- Pressure tested new 12” watermain along E 23rd Street and north along TH 169 up to new hydrant.
- Continued steam work in exposed vaults.
- Week of June 22nd
- Completed watermain connections in Brooklyn Drive.
- Installed new hydrant near Brooklyn Drive.
- Completed watermain connections from E 23rd Street to 12th Ave E.
- Week of June 15th
- Complete north and south watermain connections and service at 11th Ave E and 23rd Street.
- Complete watermain connection at 12th Ave E and 23rd Street
- Week of June 8th
- Completed watermain connections on north and south crossings of 10th Ave E and E 23rd Street.
- Directionally drilled all 12” mainline watermain.
- Completed watermain connection on E 23rd Street to north run of 12” watermain along HWY 169.
- Week of June 1st
- Mill pavement in entire project area.
- Continued work to expose steam vaults and tunnel. ( N5, N6, N7)
- Installed new 6” valve on Brooklyn Dr.
- Established connections to temporary water system on Brooklyn Dr.
- Started other project area removals.