Hibbing Water Main Capital Improvement Plan
Project Status: Active

Existing Infrastructure: 1920’s installed cast iron water main & 20 known lead service lines.
Qualifying Factors: This project was selected due to the high concentration of lead service lines at these blocks. The water main serving these blocks are additionally expected to be more than a century old.
Scope of Work: Direct replacement of ~1,600 Linear Feet of water main with modern HPDE water main and replacement of lead service lines.
Cost: Preliminary Engineering Estimate of $3.5 million
Weekly Project Updates
- Week of September 7th (Planned)
- Sub-cut and road building on the 2100 block of 4th Ave. W
Past Weeks –
- Week of August 31st
- Replacement of the remaining water services on the 2000 block of 4th Avenue W.
- Pressure test of the watermain and the services on the 2000 block of 4th Avenue W.
- Sub cut and road building on the 2100 block of 4th Avenue W.
- Week of August 24th
- Installation/replacement of the remaining water services on the 2100 block of 4th Avenue W
- Pressure test was preformed and passed on the watermain and services.
- All residents were taken off temporary water and are now being serviced from the newly installed watermain/services.
- Installation/replacement of water services on the 2100 block of 4th Avenue W.
- Installation/replacement of the remaining water services on the 2100 block of 4th Avenue W
- Week of August 17th
- Completion of the installation of watermain on the 2000 Block of 4th Avenue W.
- Bacteria and pressure testing was completed and passed on the watermain on the 2100 and block of 4th Avenue W.
- 3 services were installed on the 2100 block of 4th Avenue W.
- Lead service Line to 220 W Howard Street was replaced from the corporation stop to the water meter.
- Week of August 10th
- Installation of watermain on the 2100 Block of 4th Avenue W.
- Removals on the 2000 block of 4th Avenue W.
- Watermain Connections on 4th Avenue W and 22nd Street.
- Watermain connections on 4th Avenue W and Grant & 19th Street.
- Week of August 3rd
- Remainder of tree and stump removals on the 2000 and 2100 blocks of 4th Avenue W.
- Pavement, curb, and sidewalk removals on the 2000 and 2100 block of 4th Avenue W.
- Testing of temporary water system of 2000 and 2100 blocks of 4th Avenue W and switching over residents to temporary water pending negative bacteria testing.
- Week of July 27th
- Tree removals on the 2000 and 2100 blocks of 4th Avenue W